Skip to main content
Start of main content

Millbrook Power Project

Management and coordination of all environment documents

  • Bedford, United Kingdom

    Bedford, United Kingdom

Supported the submission of a development consent order application

The Millbrook Power project, when complete, will include a 299 megawatt gas fired peaking power plant and associated high pressure gas connection and 400 kilovolt underground electrical connection. The power generation plant and new substation will be located within Rookery South Pit, a former clay extraction site. The gas and electrical connections would be sited on agricultural land to the south. 

Millbrook Power Ltd. Brought us in on the early stages of the project, and we assisted in assessing the initial feasibility of the site. We then managed all pre-examination planning and environmental work. This included liaison with the Planning Inspectorate, local authorities, and other statutory consultees. We also managed the planning statement and consultation report, the statutory and non-statutory consultation phases, and the environmental assessment process—producing all technical environmental impact assessment sections. 

After that was complete, we were retained by Millbrook Power Ltd. to support them through the examination of the project and to manage the discharge of all development consent order requirements. 

When the Millbrook Power project is finalized, the plant will provide backup power to other sources of electricity, including renewables such as wind turbines and solar farms.   

At a Glance

Offices
Client
  • Millbrook Power Ltd

We’re better together

  • Become a client

    Partner with us today to change how tomorrow looks. You’re exactly what’s needed to help us make it happen in your community.

  • Design your career

    Work with passionate people who are experts in their field. Our teams love what they do and are driven by how their work makes an impact on the communities they serve.

End of main content
To top